Marabou Construction Update
From Marabou: In construction news, two of our six owners' cabins, Sundance Cabin and Riffle Cabin, are both vertical with Sundance Cabin having windows, electrical, and plumbing installed. Sheet rock will be hung by the end of the week. The Riverhouse Lodge and River's Edge Fitness Center have all been framed and are vertical. The RiverÂs Edge Fitness Center will have a roof within the week.
Stream restoration has been progressing steadily. The Army Corps of Engineers has recently approved phase one of the river restoration project. The roads have been coming along with over 90 percent of the sub-grade laid. The water main is also being installed at this time with over 75 percent of the water main now complete. The ranch is easily accessible with a four wheel drive vehicle.
Labels: Marabou Ranch, Marabou Ranch News, Steamboat Springs Ranch